The weather finally cooperated and we had some dry days. Ryan and Doug were able to finish the plumbing. Here are some pictures of the plumbing and one of Jaina in here "room."
Thursday, May 16, 2013
Tuesday, May 7, 2013
From adobe to soup
Our basement has gone from adobe (sun baked clay) that is very difficult to dig to a soupy mess, also difficult to dig. We are hoping that a few days of sun will find a happy medium.
Ryan and Doug are digging the trenches and laying pipe for the basement plumbing. The next step will be more foamboard and the tubing for the in floor heat. Finally, the basement slab will get poured.
Thursday, May 2, 2013
Should not have complained...
...about the rain. Yes, it is snowing...a lot...on May 2...after an 86 degree day earlier in the week. I guess this will make it easier to dig the trenches for the plumbing.
Foamboard
Ryan and Doug put foamboard along the outside of the basement foundation. This will help with keeping it even more water tight and really insulated.
Wednesday, April 24, 2013
Basement walls!
When the weather cooperates, things move fast! We stopped by the house today and the forms were off and the waterproofing applied. Ryan will be putting foam board on the outside and taking final measurements before ordering our floor trusses.
Forms and pouring
They poured the concrete for our basement walls! Ryan was out on Monday and they had gotten the muddy mess cleaned up. They were setting the forms up and poured yesterday.
Sunday, April 21, 2013
A little bit of rain..
...makes a big mess. In two days, we had around 3-4 inches of rain. While it was good to fill the ponds, the collapse of one of our walls was not so good.